# Work Breakdown Structure (WBS) Guide: Steps & Rules

> Learn what a work breakdown structure (WBS) is, the two types, the 100% and 8/80 rules, and how to build one with timelines, boards, and calendars.

Source: https://asana.com/resources/work-breakdown-structure

## Work breakdown structure (WBS) guide: Steps &amp; rules

#### Summary

A work breakdown structure (WBS) is a project management tool that helps you break down complex projects into smaller, manageable parts arranged in a clear order. In this guide, you’ll learn about the main parts of a WBS, the two main types (deliverable-based and phase-based), important principles like the 100% and 8/80 rules, and how to create your own WBS using timelines, Kanban boards, or calendars.A work breakdown structure (WBS) is a way to visually break down a project. It starts with the overall scope and shows each deliverable, making it clear how everything fits into the main project.

Since a work breakdown structure is displayed visually, it can be created using a combination of [workflow management software](/uses/workflow-management) and project management frameworks. Some of these methods include timelines, [Kanban boards](/resources/what-is-kanban), and calendars.

In this guide, we’ll explain how to create a work breakdown structure, what to include, and give examples you can use in your own projects.

#### Master AI-Powered Workflow Optimization

Ready to revolutionize your team's productivity with AI you can trust? Join industry leaders from Asana and Anthropic to learn proven strategies for implementing AI across your workflow stages and unlock the full potential of Asana's AI Studio.
- [Watch the webinar](https://resources.asana.com/how-to-transform-your-workflows)

## What is the work breakdown structure in project management?

A work breakdown structure (WBS) is a [hierarchical decomposition](/resources/top-down-approach) of a project's total scope into smaller, manageable deliverables. It visually organizes work from the top-level objective down to individual tasks, making it easier to plan, assign, and track progress.

Every WBS is made up of a few core components:
- A [project baseline](/resources/project-baseline) or scope statement, which includes a [project plan](/resources/project-management-plan), description, and name
- [Project stakeholders](/resources/project-stakeholder)
- An organized [project schedule](/resources/project-timeline-schedules)
- [Project deliverables](/resources/what-are-project-deliverables) and supporting subtasks

[Project managers](/resources/become-a-project-manager) use work breakdown structures to help teams break down complex [project scopes](/resources/project-scope), [visualize projects and dependency-related deliverables](/resources/visual-project-management-kanban-timeline-calendar), and give team members a visual project overview.

From there, you'll organize your structure based on the hierarchical levels of sub-deliverables. Your project might also include phases based on the work needed and the overall [project timeline](/resources/create-project-management-timeline-template).

### The 2 types of WBS
- **Deliverable-based WBS:** This method breaks work into deliverables that support the main project goal. It works best for shorter projects with clear outcomes, like creating an annual revenue report.
- **Phase-based WBS:** This method organizes work into phases, with each phase containing groups of tasks done in stages. It’s helpful for longer projects with less defined outcomes, like increasing retention by 20% over three years.

## Why use a WBS in project management

A WBS gives your team a clear way to plan and execute complex projects. Breaking large initiatives into smaller pieces helps you control [scope, timelines, and resources](/resources/project-controls) more effectively.

Key benefits of using a WBS include:
- **Improved scope control:** Defining every deliverable upfront reduces the risk of scope creep and [missed requirements](/resources/requirements-management).
- **More accurate estimates:** Breaking work into smaller components makes it easier to estimate time and costs.
- **Better team alignment:** Everyone can see how their work contributes to the overall project objective.
- **Clearer accountability:** Assigning owners to each work package ensures nothing falls through the cracks.
- **Easier progress tracking:** You can monitor completion at each level to identify potential delays early.

No matter if you’re running a product launch, construction job, or marketing campaign, a WBS helps turn your ideas into clear, actionable steps.

#### 3 ways to transform your enterprise project management

Watch a live demo and Q&amp;A session to help you streamline goal-setting, accelerate annual planning, and automate how teams intake strategic work.
- [Watch the webinar](https://resources.asana.com/transform-your-enterprise-project-management.html?utm_medium=web&amp;utm_source=resource-card&amp;utm_campaign=ops24-demo-webinar)
- [Watch the webinar](https://resources.asana.com/transform-your-enterprise-project-management.html?utm_medium=web&amp;utm_source=resource-card&amp;utm_campaign=ops24-demo-webinar)

## What are the 3 levels of work breakdown structure?

The levels in a WBS help separate tasks based on their dependencies. Because every project is different, your WBS levels may vary as well.

Most WBS structures have three main levels of dependencies, but you might need more or fewer. Each level links to a parent task, and work is organized by these connections.

### **Level 1: The parent task**

The first level of a WBS is the simplest version of the project. It includes the parent task, which is usually the main project goal.

For example, if your project team is revamping your website design, the first level might look like this:
- Launch new website design

Level one is the basic objective and the first step of your many [project management phases](/resources/project-management-phases). The work needed to complete this objective comes in levels two and three.
- [Read: How to write an effective project objective, with examples](/resources/how-project-objectives)

### **Level 2: Dependencies and tasks**

Level two of your WBS lists the subtasks, or dependencies, of the main task. This level can become more detailed depending on your project’s scope.

For example, here are tasks needed to launch a new website design:
- Host a creative [brainstorming](/resources/brainstorming-techniques) session
- Revamp brand guidelines
- Create a messaging approach
- Redesign your logo
- Add new photography

Level two gives a more detailed view than level one, but it still provides a high-level overview of the main dependencies needed to finish the project.

### **Level 3: Subtasks**

At the third level of the WBS, you break down dependencies into smaller, actionable tasks. This is usually the most detailed level, where you define the specific tasks that make up your deliverables.

Continuing the above example, here are the level three tasks for a new site design:
- Choose brand colors
- Build a brand mood board
- Assign UX designers
- Build a mockup design
- Review and approve mockups
- Schedule a brand photoshoot
- Resize and edit pictures

You can add more levels to your WBS to include more detail in your visual breakdown.

## Key WBS principles

To build a strong WBS, it helps to know two key principles that guide how you break down and organize your project work.

### The 100% rule

The 100% rule is the most important part of building a WBS. It means your WBS should include all the work in the project scope, nothing extra and nothing missing.

This rule applies at every level of the hierarchy. Each parent element must account for all the work in its child elements. If a task isn't in the WBS, it's not part of the scope. This prevents gaps and [scope creep](/resources/scope-management-plan).

### The 8/80 rule for work packages

The 8/80 rule helps you decide how big each work package should be. Ideally, a work package should take between 8 and 80 hours to finish.
- **Less than 8 hours:** You've likely broken the work down too finely, creating unnecessary complexity.
- **More than 80 hours:** You need to decompose the work further for better visibility and control.

This rule isn’t strict, but it’s a helpful guideline for finding the right amount of detail.

## What's included in a work breakdown structure?

A work breakdown structure organizes your project deliverables in a visual hierarchy. Key elements include objectives, deliverables, timelines, and stakeholder assignments, similar to what you'd find in a [project charter](/resources/project-charter), but focused on the scope breakdown.

Before you make your own WBS, it’s important to know what to include. Here are the main parts you should add.

### WBS dictionary

A WBS dictionary is a document that explains each part of your WBS in detail. Since the visual chart can’t show everything, the dictionary gives your team the details they need. Consider involving team members from [various departments](/resources/breaking-down-silos) when creating it to ensure accuracy and usefulness.

Some fields you should include in your dictionary are:
- **Task names:** Keep this clear and simple, a few words at most.
- **Descriptions:** Go into a little more detail, but no more than a sentence or two.
- [Deliverables](/resources/what-are-project-deliverables)**:** Be clear about what you're expecting the team to complete.
- [Budget](/resources/project-budget)**:** Your projected expenses, including how much you'll spend, for what, and by when.
- [Milestones](/resources/project-milestones)**:** Significant moments on the project timeline where a batch of tasks is completed.
- **Approvals:** Which tasks, if any, require approval?

### Task description

Task descriptions should have a task name and a short summary of the goal. If you need to add more details, you can put them in your WBS dictionary. The aim is to make it easy for team members to quickly understand each task.

### Task owner

Assigning a task owner is important for accountability and communication. This way, everyone knows who to contact with questions.

While project managers often serve as task owners, department heads and managers may own specific tasks depending on the work. Clear ownership improves [team productivity](/resources/ways-improve-team-efficiency-work) by eliminating time wasted searching for answers.

### Task budget

If your project has a large budget, track it closely. Setting budget limits for each task makes it easier to see how you’re doing compared to your total budget. Not tracking your budget can lead to spending more than you anticipated. Be sure to track both your total budget and the costs of individual tasks.

### Completion date

It’s important to track when tasks are finished, but be ready to adjust as your project changes.

Break down each task in a timeline or [project management tool](/uses/project-management) to track progress effectively. This helps you catch delays early and prevent deadline issues from compounding when you [manage multiple projects](/resources/managing-multiple-projects).

### Task status

Documenting [task status](/resources/how-project-status-reports) is important for quick progress checks. Many teams use terms such as open, in progress, and complete.

This helps track progress and gives a high-level overview of team productivity. If there's a pattern of teams unable to complete tasks, you can address [team workload](/resources/effectively-manage-team-workload) or communication issues early.
- [Read: How to write an effective project status report](/resources/how-project-status-reports)

#### Nucleus Research: Cut project time in half with Asana

In this independent study, learn how Asana can reduce the time it takes to complete a project by 50%, minimize project errors by up to 90%, and more.
- [Get the insights](/resources/nucleus-research)
- [Get the insights](/resources/nucleus-research)

## How to create a work breakdown structure

Since a WBS is presented as a visual hierarchy, you have several options for creating yours. To save setup time, start with a [work breakdown structure template](/templates/work-breakdown-structure) already formatted for timelines, boards, or calendars.

Popular visual methods are timelines, Kanban boards, and calendars. Let’s look at how each one works.

### Timelines (or Gantt charts)

Timelines provide excellent visual clarity for WBS planning. Here are the key functions you get using a timeline view, also known as a [Gantt chart](/resources/gantt-chart-basics):
- Import [traditional spreadsheets](/resources/excel-timeline-calendar-alternative)
- Track progress
- Adjust tasks
- Connect tasks by dependencies
- Adjust deadline shifts
- Assign task owners
- Store unscheduled tasks
- Adjust color tracking
- Section by levels
- Filter and sort tasks

You can start your WBS by [importing an existing spreadsheet](/apps/csv-importer) or building it directly in [timeline software](/features/project-management/project-views). It's up to you to decide which visual is right for your team.

### Kanban boards

Kanban boards are similar to timelines but are organized vertically like boards instead of horizontally. [Kanban software](/uses/kanban-boards) can help with the following:
- Track progress
- Adjust tasks
- Connect tasks by dependencies
- Adjust deadline shifts
- [Plot workflows](/resources/workflow-examples)
- [Communicate in one place](/resources/effective-communication-workplace)
- Plan [product roadmaps](/templates/product-roadmap)

A Kanban board is one of the most frequently used tools for day-to-day [resource management](/resources/resource-management-plan). You can see task details up front, making it a great option if you can't create a WBS dictionary.

### Calendars

The third option is using [team calendar software](/uses/team-calendar). While not as commonly used for breakdown structures, calendars are helpful for switching between day, week, and month views for large projects.

To build your WBS with a calendar, you can import a spreadsheet or start a new project directly in your calendar tool.
- [Read: 3 visual project management layouts (and how to use them)](/resources/visual-project-management-kanban-timeline-calendar)

## Common WBS mistakes to avoid

Even experienced project managers can make mistakes when building a WBS. Here are some common pitfalls to avoid:
- **Turning the WBS into a task list:** Focus on deliverables and outcomes, not step-by-step activities. List what you're producing, not actions like "schedule meeting."
- **Over-decomposition:** Breaking work down too finely creates unnecessary complexity. Use the 8/80 rule as your guide.
- **Ignoring the WBS after planning:** Your WBS is a living document. Update it as the [project scope evolves](/resources/change-control-process).
- **Violating the 100% rule:** Gaps in your WBS mean work will fall through the cracks. Account for every deliverable.

## Work breakdown structure example

Now that you know what goes into a WBS and how to build one, let's look at a tangible example. While your template will look different depending on the method you use, your WBS should include similar task hierarchies and levels.

Here is an example work breakdown structure to get you started:

**WBS name:** Website design

**Description:** Revamp our old website design to align with the new branding.

**Completion date:** 9/15/21

**Budget:** $50,000

**Level 1:**
- _Revamp website design_

**Level 2:**
- _Revamp brand guidelines (Complete)_
- _Create messaging approach (Complete)_
- _Redesign logo (In progress)_
- _Add new photography (Open)_

**Level 3:**
- _Revamp brand guidelines_
- _Brand colors, Kat Mooney_
- _Brand mood board, Kat Mooney_
- _Design UX, Ray Brooks_
- _Create a messaging approach_
- _Headline, Daniela Vargas_
- _Mission statement, Daniela Vargas_
- _Language guidelines, Daniela Vargas_
- _Redesign logo_
- _Sketch, Kabir Madan_
- _Mockups, Kat Mooney_
- _Final designs, Kat Mooney_
- _Add new photography_
- _Photoshoot, Kabir Madan_
- Photo edits, Kat Mooney
- _Final selections, Kabir Madan_

Remember that your WBS will look different depending on the project's size, complexity, timeline, and your chosen software.

## Build your work breakdown structure with confidence

A work breakdown structure isn't hard to create once you get the hang of it. By adding a visual hierarchy to your project, you and your team gain clarity and focus on work that matters.

With Asana, you can easily switch between lists, timelines, boards, and calendars without missing a beat. Spending less time on busywork means more time for impactful work. [Get started](/create-account) and see how Asana can help you build better projects.
- [See Asana in action](/demo/main)

## Frequently asked questions about work breakdown structures

#### What is the 8/80 rule in project management?

The 8/80 rule states that each work package in a WBS should take between 8 and 80 hours of effort to complete. Packages outside this range are either too granular or too broad for effective tracking.

#### What is the difference between WBS and CBS?

A WBS defines what work will be done by organizing deliverables hierarchically. A CBS (cost breakdown structure) is its financial counterpart, mapping costs to each WBS element for budget tracking.

#### What is the difference between a WBS and a project plan?

A WBS is a hierarchical breakdown of project deliverables showing what needs to be produced. A project plan is a broader document that includes the WBS plus timelines, resources, and risk management strategies.

- [Project management](/resources/project-management)

- [Project portfolio management 101](/resources/what-is-project-portfolio-management)

Project management

Business strategy

#### Writer

If you manage various initiatives across different teams and departments, you know how hard it can be to capture progress and share results in one place. Project management tools ...

- [Asana app in ChatGPT: go from ideas to action](/resources/chatgpt-asana-integration)

AI at work

#### Content writer

You just spent 30 minutes in ChatGPT working through an idea — outlining a campaign, mapping out next steps, pressure-testing a plan.It’s clear, structured, and actually feels rea ...

- [How to set and achieve project milestones](/resources/project-milestones)

Project management

Goals

#### Head of Content, Asana

Not all project plans are created equal. You may have goals, tasks, task owners, and deadlines. You may have dependencies and deliverables. But did you remember to include project ...

- [10 team management skills to start building today](/resources/team-management-skills)

Leadership

Project management

Collaboration

Inspire &amp; Impact Collection

#### Writer

What sets a good manager apart from a bad one? It isn't the work you do or the workflows your team uses. Rather, good managers focus on their team. By prioritizing supporting your ...

- [Work breakdown structure (WBS): what it is and how to use it](/resources/work-breakdown-structure)

Project management

Project management

- [Content writer](/author/alicia-raeburn)

A work breakdown structure (WBS) is a way to visually break down a project. It starts with the overall scope and shows each deliverable, making it clear how everything fits into t ...